Van Ness Improvement Project Construction Forecast: April 5 - April 16, 2021

Service Affected
Accessibility
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking

Photo of workers smoothing concrete in the median on Van Ness Avenue

Workers smooth concrete in median at Van Ness Avenue at Pine Street for the Van Ness Improvement Project.

Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block east of Van Ness Avenue, is a recommended alternative for people traveling by bicycle in the area.
 
At times, bus stops along Van Ness Avenue and its side streets need to be relocated to perform construction for the Van Ness Improvement Project. Signage directs riders to temporary stops.
 
The work listed below is scheduled for daytimes, 7:00 a.m. to 8:00 p.m. Planned night work is italicized. The night shift for construction is 8:00 p.m. to 7:00 a.m. During this time, neighbors are advised to anticipate construction-related noise and vibrations as crews work diligently to complete necessary night work.

 
The following Van Ness Improvement Project construction forecast is subject to change. For more project details, please visit SFMTA.com/VanNess. In the next two weeks crews are scheduled to work on overhead power installations, traffic signal wiring & hardware installation, light pole setting and related work. 
 
 
Monday through Friday, April 5 through April 9

  • Bay to Francisco. *Disruptive noise is expected. 
  • Francisco to Chestnut. *Disruptive noise is expected.
  • Chestnut to Lombard. *Disruptive noise is expected. 
  • Lombard to Greenwich. *Disruptive noise is expected. 
  • Greenwich to Filbert. *Disruptive noise is expected. 
  • Filbert to Union. *Disruptive noise is expected. Street base work scheduled at Union intersection will partially close intersection at times.
  • Union to Green. *Disruptive noise is expected. Street base work scheduled at Union intersection will partially close intersection at times.
  • Green to Vallejo. *Disruptive noise is expected. 
  • Vallejo to Broadway. *Disruptive noise is expected. 
  • Broadway to Pacific. *Disruptive noise is expected. 
  • Pacific to Jackson. *Disruptive noise is expected. 
  • Jackson to Washington. *Disruptive noise is expected. 
  • Washington to Clay. *Disruptive noise is expected. 
  • Clay to Sacramento.  *Disruptive noise is expected. 
  • Sacramento to California. *Disruptive noise is expected. 
  • California to Pine. *Disruptive noise is expected. 
  • Pine to Bush. *Disruptive noise is expected.  
  • Bush to Sutter. *Disruptive noise is expected. 
  • Sutter to Post. *Disruptive noise is expected. 
  • Post to Geary.*Disruptive noise is expected. 
  • Geary to O'Farrell. *Disruptive noise is expected. 
  • O'Farrell to Ellis. *Disruptive noise is expected. 
  • Ellis to Eddy. *Disruptive noise is expected. 
  • Eddy to Turk. *Disruptive noise is expected. 
  • Turk to Golden Gate. *Disruptive noise is expected. 
  • Golden Gate to McAllister. *Disruptive noise is expected. 
  • McAllister to Grove. *Disruptive noise is expected. 
  • Grove to Hayes. *Disruptive noise is expected. 
  • Hayes to Fell. *Disruptive noise is expected.  
  • Fell to Market. *Disruptive noise is expected. 
  • Market to Mission. *Disruptive noise is expected. 

 
Monday through Friday, April 12 through April 16
Traction power cable pull to be performed between Chestnut Street and Marina Boulevard.

  • Bay to Francisco. *Disruptive noise is expected.
  • Francisco to Chestnut. *Disruptive noise is expected.
  • Chestnut to Lombard. *Disruptive noise is expected.
  • Lombard to Greenwich. *Disruptive noise is expected.
  • Union to Green. *Disruptive noise is expected.
  • Green to Vallejo. *Disruptive noise is expected.
  • Vallejo to Broadway. *Disruptive noise is expected.
  • Broadway to Pacific. *Disruptive noise is expected.
  • Pacific to Jackson. *Disruptive noise is expected.
  • Jackson to Washington. *Disruptive noise is expected.
  • Washington to Clay. *Disruptive noise is expected.
  • Clay to Sacramento.  *Disruptive noise is expected.
  • Sacramento to California. *Disruptive noise is expected. Street base work scheduled at California Street intersection will partially close intersection at times.
  • California to Pine. *Disruptive noise is expected. Street base work scheduled at California Street intersection will partially close intersection at times.
  • Pine to Bush. *Disruptive noise is expected.
  • Bush to Sutter. *Disruptive noise is expected.
  • Sutter to Post. *Disruptive noise is expected.
  • Post to Geary.*Disruptive noise is expected.
  • Geary to O'Farrell. *Disruptive noise is expected.
  • O'Farrell to Ellis. *Disruptive noise is expected.
  • Ellis to Eddy. *Disruptive noise is expected.
  • Eddy to Turk. *Disruptive noise is expected.
  • Turk to Golden Gate. *Disruptive noise is expected.
  • Grove to Hayes. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m. 
  • Hayes to Fell. *Disruptive noise is expected. Night work is scheduled Monday through Friday between the hours of 8:00 p.m. and 7:00 a.m. 
  • Market to Mission. *Disruptive noise is expected.