Serving more than 24,000 people daily, the Balboa Park BART and Muni Station and the surrounding area is one of the busiest transit hubs in the region located near the I-280 Ocean-Geneva Ave interchange. With so much transportation activity, this project aims to improve the safety and accessibility for pedestrians, bicyclists, motorists and intermodal travelers, in addition to some streetscape improvements and maintenance upgrades.

Key improvements include a landscaped median, sidewalk widening and red transit-only lanes on Geneva Ave, as well as installations of pedestrian lighting, curb ramps and new wayfinding signs around the station. Flashing beacons will also be added to the Ocean Ave I-280 off ramp and the two poles will be relocated to improve accessibility of the walkway.

Upcoming meetings

No upcoming meetings have been posted

Latest updates

Project Details

INTRODUCTION

Balboa Park Station and the surrounding area is one of the busiest transit hubs in the region, serving more than 24,000 people daily. It has one of the highest ridership BART stations outside of downtown San Francisco. The site is the terminus for three light rail routes and is served by several Muni bus lines. The area also encompasses the I-280 Ocean-Geneva Avenue system with multiple on- and off-ramps. The SFMTA Green Yard, used for storage and maintenance of light rail vehicles, is also located adjacent to the station. Regional attractions within walking distance include the San Francisco City College campus, Balboa Park and several other middle and high schools.

With such a busy and multi-faceted hub of transportation activity, this project aims to improve the safety and accessibility for pedestrians, bicyclists, motorists and intermodal travelers, in addition to some streetscape improvements and maintenance upgrades.

IMPROVEMENTS

  • Sidewalk widening on Geneva Avenue to provide more space for pedestrians

  • Expansion of the existing median on Geneva Ave, including the installation of landscaping for pedestrian safety

  • Red transit-only lanes on Geneva Avenue (between Delano Avenue and I-280) to improve transit service and reliability

  • Improved pedestrian crossing on Ocean Ave near I-280 on-ramp where the K & J lines enter the Green Light Rail Center, to enhance accessibility and improve pedestrian safety

  • Pedestrian lighting along the perimeter of the Balboa Park Station to increase transit customer safety and visibility.

  • Flashing beacon system on the I-280 Ocean Avenue off-ramp to improve pedestrian safety by warning drivers of pedestrians crossing the off-ramp

  • Relocation of the Overhead Contact System poles off the J/K walkway to improve safety and accessibility

  • Additional signs around the Balboa Park Station to increase customer awareness of transit options in the area

  • Americans with Disabilities Act (ADA) compliant curb ramps on Ocean Avenue and Geneva Avenue

  • Resurfacing of Geneva Avenue between San Jose Avenue and I-280  

  • Upgrading of the traffic and train signaling system.

Map of work scope for project

PROJECT TIMELINE

Detail Design Phase Mar 2014 – Mar 2015
Advertised Contract April 2015
Awarded Contract August 2015
Notice to Proceed (NTP) Jan 25, 2016
Start of Construction February 29, 2016
Construction Complete (tentative) Oct 2016

WHAT TO EXPECT DURING CONSTRUCTION

Area impacts are expected, including noise, dust and moving vehicles. Other impacts may also include traffic delays, parking restrictions, bus stop relocations, traffic routing, pedestrian detours and transit service changes.

General construction working hours are 7 a.m. to 4:30 p.m. Major impacts are scheduled to avoid disruption of weekday, peak-hour congestion.

We will consistently work with the contractor to minimize any disruptions to the community and mitigate concerns.

BACKGROUND

  • The San Francisco Board of Supervisors adopted the Balboa Park Station Area Plan in 2009, which has served as a template for all development activities in the area.

  • In October 2012, the Balboa Park Station Capacity and Conceptual Engineering Study was completed to refine and advance the Balboa Park Station Area Plan from a vision to a reality, improving the area around the Balboa Park Station.

Objective: To implement safety, accessibility, and transit improvements around the Balboa Park Station to enhance the customer experience in one of the regions busiest multimodal facilities

Contacts