View of the final design of the Castro Muni Station accessibility elevator that includes a 4th level added to Market Street Newly designed Accessibility elevator for the Castro Muni Station and...
The three pictures below were different design options considered for the new station elevator. All options were made of glass to allow station agents to see into the elevator cab and maintain...
ConnectSF , which is comprised of staff from the SFMTA, the San Francisco County Transportation Authority and the San Francisco Planning Department, recently published a strategy for reinvesting in...
Details of Work Performed: L Bus Serves regular stops: As we are wrapping up the major infrastructure improvements on Taraval Street, the L bus is now serving the regular stops between Sunset...
Mark Your Calendars! From April 22 through May 13, the SFMTA is hosting a virtual open house as one way to provide information about the project proposals and collect public feedback about proposed...
The SFMTA is hosting a Virtual Engineering Public Hearing for the Anza Street Bike Lanes Project on Friday, April 30, at 10:00 am. You may access this event by visiting SFMTA.com/ENGHearing or, to...
Following approval of a project corridor, SFMTA’s Temporary Emergency Transit (or high-occupancy vehicle) Lanes will be evaluated once they are installed. Evaluation criteria provided by the...
Photo: Looking south at crew member laying concrete between Eddy and Larch on Van Ness. Construction Forecast for March 8 to March 19, 2021 Those traveling on the corridor are advised to stay alert...
Photo: Crew members laying concrete on the southwest corner at Van Ness and Sutter Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk...
Photo: Crew members w orking to replace light poles at southwest corner of Post and Van Ness Those traveling on the corridor are advised to stay alert and allow more travel time during construction...
Crew member installing irrigation sleeves along Van Ness at Broadway Those traveling on the corridor are advised to stay alert and allow more travel time during construction. Polk Street, one block...
Workers smooth concrete in median at Van Ness Avenue at Pine Street for the Van Ness Improvement Project. Those traveling on the corridor are advised to stay alert and allow more travel time during...
The Embarcadero Quick-Build Projects at Pier 35, Ferry Terminal, and in the Rincon Restaurant Zone were substantially completed in December to expedite safety and mobility improvements along the...
Photo: Crew member laying new pavers in the center median at Geary and Steiner streets. As part of the Geary Rapid Project , work to replace aging water lines, in coordination with San Francisco...
Photo: Crew members spreading concrete for the new bus pad at O’Farrell and Van Ness. Geary Rapid Project Construction Forecast: March 13 – March 26, 2021 As part of the Geary Rapid Project , work...
Photo: Viewpoint from the north end of the pedestrian bridge on Geary at Webster of the future surface level crosswalk which will supplement the bridge. As part of the Geary Rapid Project , work to...
Photo: Crews working to install new ADA curb ramp at Leavenworth and Geary. As part of the Geary Rapid Project , work to replace aging water lines, in coordination with San Francisco Public...
Work Forecast Plan for the Weeks of March 1 to March 12, 2021 Details of Work Performed: HEADSUP: Street repaving is planned for: March 15-23 between Sunset Boulevard and 46th Avenue. Traffic control...
Thanks to all who participated with the Anza Street Bike Lanes Project and for sharing your feedback! If you submitted comments or questions via the online survey or by email, or if you would like to...
Update for January 2021 While the 6th Street Pedestrian Safety Project is moving forward, this month we want to update you on changes coming to Market Street which will add to the safety and...
Details of Work Performed: Taraval Street repaving: Due to the inclement weather, the start of street repaving planned for Monday, March 15 is pushed to Tuesday, March 16. To compensate a day lost,...
In October 2019, the Better Market Street project finished its California Environmental Quality Act (CEQA) and National Environmental Policy Act (NEPA) environmental review and received project...
The San Francisco Municipal Transportation Agency (SFMTA) is initiating a quick-build traffic safety project on South Van Ness Avenue between 14th Street and Cesar Chavez. This project is part of the...
Details of Work Performed: Update on Taraval Street repaving: Grinding and paving have been successfully completed on the south side of Taraval Street and part of the north side. On March 29 and 30,...