L Taraval Improvement Project Work Forecast November 1 - November 14, 2020

Service Affected
Driving
Transit
Walking
Neighborhoods Affected

Work Forecast Plan for the Weeks of November 1 to November 14, 2020

Details of Work Performed:
  • Street restoration work is planned for:
    • November 2-7 and November 9-14 at the intersection of 37th Avenue and Taraval
    • November 2-7 and November 9-14 at the intersection of 38th Avenue and Taraval
    • November 2-7 and November 9-14 at the intersection of 39th Avenue and Taraval
    • November 2-7 and November 9-14 at the intersection of 44th Avenue and Taraval
    • November 2-7 and November 9-14 at the intersection of 45th Avenue and Taraval
  • Construction of curb ramp work is planned for:
    • Starting November 2 between 40th Avenue and Sunset Boulevard
  • Continuation of waterline work is planned for:
    • November 2-6 and November 9-13 between 44th and 43rd Avenue 
    • November 4-6 and November 9-13 between 48th and 46th Avenue 
  • Concrete street base work is planned for:
    • November 12 between 40th and 39th Avenue from 8:00 a.m. to 7:30 p.m.
  • Construction of accessible boarding platform is planned for:
    • November 2-6 and November 9-13 at Taraval Street and Sunset Boulevard
  • Track replacement work is planned for: 
    • November 2-6 and November 9-13 between 46th and 43rd Avenue
    • Starting November 10 at the intersection of 46th Avenue and Taraval 
  • Transfer of guy wires from existing poles to new poles is planned for: 
    • November 1-6 on 46th Avenue between Vicente and Wawona Street from 10:00 p.m. to 6:00 a.m.
    • November 1-6 at the northeast corner of 46th Avenue and Wawona Street from 10:00 p.m. to 6:00 a.m.
    • November 1-6 at the southeast corner of 46th Avenue and Vicente Street from 10:00 p.m. to 6:00 a.m.
    • November 1-6 at the southwest and southeast corner of 47th Avenue and Wawona from 10:00 p.m. to 6:00 a.m.
  • Replacement of overhead contact system (OCS) wires is planned for:
    • November 11-13 on 46th Avenue between Taraval to Wawona Street from 10:00 p.m. to 6:00 a.m.
    • November 11-13 on Vicente Street between 46th to 47th Avenue from 10:00 p.m. to 6:00 a.m.
    • November 11-13 on 47th Avenue between Wawona to Vicente Street from 10:00 p.m. to 6:00 a.m.
    • November 11-13 on Wawona Street between 46th to 47th Avenue 10:00 p.m. to 6:00 a.m.
What to Expect:

Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.

Heavy vibrations from the shoring and sheet piling work is expected for open trench work.

Time of Work:
  • Monday to Friday 8:00 a.m to 5:00 p.m.; Saturday to Sunday 8:00 a.m to 5:00 p.m. Hours subject to change based on construction needs. Please refer to project forecast for construction hours.
  • Night work starting Sunday, October 11 to Tuesday, November 24 from 10:00 p.m. to 6:00 a.m. Please refer to project forecast for indicated night work. 
Traffic Impacts:

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified during active work.

Starting Tuesday, November 10, track replacement work will begin at the intersection of 46th Avenue and Taraval Street. For the track replacement work, the intersection of 46th Avenue and Taraval Street will be closed to vehicular traffic at all hours until the work is complete---approximately one month. Signage will be in place to alert drivers to detour before they approach the intersection.

On Thursday, November 12 from 8:00 a.m. to 7:30 p.m., both sides of Taraval Street between 40th Avenue and Sunset Boulevard will be temporarily closed for vehicular access for one day. Signage will be in place to alert drivers to detour before they approach the work area. 

For track replacement work, traffic will be detoured at the intersections of 38th, 44th, and 45th Avenue at all times of the day until track replacement work along these segments are complete. During active construction hours, parking on both sides of the blocks will be temporarily restricted to give the crew the safety clearance they need to demo and replace the aged tracks in the center of the road and allow eastbound/westbound vehicular traffic. Parking will be returned at the end of each work day along the impacted blocks.  

   


The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at LTaravalProject@SFMTA.com or 415.646.2382

Stay Up To Date: For L Taraval Improvement Project work forecast and updates, please sign-up for email updates by visiting LTaravalProject/SFMTA.com.

Poster advertising Sunday event on Taraval Street between 46th and 47th Avenue

☎ 311 (Outside SF 415.701.2311; TTY 415.701.2323) Free language assistance / 免費語言協助 / Ayuda gratis con el idioma / Бесплатная помощь переводчиков / Trợ giúp Thông dịch Miễn phí / Assistance linguistique gratuite / 無料の言語支援 / 무료 언어 지원 / Libreng tulong para sa wikang Filipino / การช่วยเหลือทางด้านภาษาโดยไม่เสียค่าใช้จ่าย / خط المساعدة المجاني على الرقم