L Taraval Improvement Forecast and Project Segment B Update – February 27 – March 11, 2023

Route(s) Affected

L Taraval Improvement Forecast and Project Segment B Update February 27 – March 11, 2023

In the coming weeks, work continues on water and sewer lines, as well as on the overhead contact system (OCS) that powers the trains. OCS work is now focused on foundation work to prepare for the installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations. Extreme weather conditions may impact the construction schedule. 

The inbound bus stop at Taraval and 15th has been relocated across the intersection until fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. and 4:00 p.m. Construction schedules are subject to change. “No Parking” signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies are performing infrastructure work in the area. This includes work by Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

L Taraval Improvement Project – Segment B

Construction work is scheduled to be performed - February 27 – March 11, 2023

Taraval Street

15th to 17th avenues: waterline work, excavation and shoring, service lateral, service change over*

16th to 18th avenues: OCS foundation and pole work

18th to 19th avenues: sewer line work, construct manhole

17th to 19th avenues: water line work

19th to 20th avenues: water line work, excavating and shoring

24th Avenue: waterline work, excavating and shoring

28th to 29th avenues: OCS foundation and pole work

29th to 33rd avenues: water line work, excavating and shoring service laterals, chlorinate and connect segments

32nd, 33rd, 34th, 35th Avenue: demo and grade curb ramp

31st to 33rd avenues: water line work, excavating and shoring

32nd and 34th avenues: construct sidewalk and curb ramp

33rd to 34th avenues: OCS foundation and pole work

36th Avenue to Sunset Boulevard: waterline work

Ulloa Street

15th Avenue: waterline work, excavate and shore water service lateral

Ulloa and Funston: waterline work, chlorinate and connect segments

Temporary staging locations

22nd Avenue west side from Taraval to Santiago streets

24th Avenue east side from Taraval to Santiago streets

26th Avenue east side from Taraval to Santiago streets

27th Avenue west side from Taraval to Ulloa streets

33rd Avenue east side from Taraval to Santiago streets

*Water service to some properties may be briefly shut off while SFPUC connects to the new water main. SFPUC will notify properties in advance of any service interruption.