FINAL UPDATE: Delay on San Bruno btwn Harkness and Wilde has cleared. IB/OB 8/8AX and 9/9R resuming regular service. (More: 10 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

L Taraval Improvement Project Seg B Update and Forecast - October 10 - 22, 2022

Service Affected
Bicycle
Motorcycle
Parking
Taxi
Driving
Transit
Walking
Route(s) Affected

L Taraval Improvement Project – Segment B

Project Update October 10 - 22, 2022

Work continues on water and sewer lines, as well as on the overhead contact system (OCS). OCS work is now focused on foundation work and installation of new poles. Construction teams will be excavating and jackhammering pavement, which may cause vibrations. Materials are also being temporarily staged nearby. Dust control and housekeeping measures are in place at active construction and staging locations.

Monday, October 17 is the target date for the relocation of the bus stop location at 15th Avenue and Taraval Street from the southwest corner to the southeast corner, in front of Kelley-Moore Paints, 445 Taraval Street. The relocation will be until the end of construction after the new tracks are laid and the L Taraval rail service is reactivated, expected in fall 2024.

General construction hours are Monday to Friday between 8:00 a.m. to 4:00 p.m. Night work below is italicized and takes place from 10 p.m. to 5 a.m. Construction schedules are subject to change. No parking signs will be posted in construction and staging areas, and intersections may be closed to through traffic on Taraval Street.

Multiple agencies in the area are performing infrastructure work. This includes Public Works on 19th Avenue, Public Utilities Commission at Vicente and Wawona streets and PG&E along Taraval Street.

The following construction work is scheduled to be performed October 10 - 22, 2022

Taraval Street

15th to 18th avenues: OCS foundation work, water line work

19th to 26th avenues: Water line work, excavate and shore

25th to 27th avenues: Sewer work

33rd to 34th avenues: Water work

Temporary staging locations

16th Avenue west side from Taraval to Ulloa streets

17th Avenue west side from Taraval to Santiago streets

26th Avenue east side from Taraval to Santiago streets

27th Avenue west side from Taraval to Ulloa streets

32nd Avenue west side from Taraval to Santiago streets

35th Avenue west side from Taraval to Ulloa streets

36th Avenue west side from Santiago to Rivera streets