L Taraval Segment B Project Update and Forecast - April 4 – April 16, 2022

SFMTA.com/LTaravalForecast
Service Affected
Accessibility
Bicycle
Parking
Driving
Walking
Route(s) Affected

Details of Work to be performed:

Project Update and Forecast for the weeks of April 4, 2022 – April 16, 2022

Taraval St.

North side of Taraval between 36th Ave. to Sunset Blvd

4/1/22 - 4/7/22 Sewer north side of 37th Ave. to Sunset Blvd.

4/11/22 – 4/15/22 Sewer work intersection north side of 36th Ave. to Sunset Blvd.

4/4/22 – 4/9/22 Sewer work intersection north side of Taraval St. and Sunset Blvd.

North side of Taraval St. between 18th to 21th avenues    

4/4/22 – 4/14/22 Sewer work north side intersection of 21st avenue

4/4/22 – 4/13/22 Sewer work north side of 21st to 20th avenues

4/11/22 - 4/15/22 Sewer work north side of 19th to 18th avenues

15th Ave. between Taraval and Ulloa streets

3/10/22 – 4/15/22 Water line west sides between Taraval and Ulloa streets                                 

Temporary staging locations

2/28/22 - 4/15/22    24th Ave. east side between Santiago and Taraval streets

2/25/22 - 4/30/22    37th Ave. east side between Rivera and Santiago streets

                                 Staging area is 10 ft. wide and approximately 250 ft. long

 2/11/22 - 4/30/22   36th Ave. east side between Rivera and Santiago streets

                                 Staging area is approximately 165 ft. long and 10 ft. wide

3/28/22 - 4/15/22     36th Ave. northwest corner between Taraval and Santiago streets

                                  Staging area is approximately 80 ft. long on 36th Avenue and 10 ft. wide.

3/18/22 - 4/8/22       34th Ave. east and west between Santiago and Taraval streets

                                  Staging area is approximately 50 ft. long and 10 ft. wide

3/16/22 - 4/16/22     22nd Ave. east and west between Santiago and Taraval streets

                                  Staging area is 10 ft. wide and approximately 70 ft. long

3/16/22 – 4/16/22    21st Ave. northwest corner of Taraval St. to Santiago

                                  Staging area is approximately 70 ft. long and 10 ft. wide

4/3/22 - 4/17/22      33rd Ave. west side between Santiago and Taraval streets

                                 Staging area is approximately 80 ft. long on 33rd Ave. and 10 ft. wide

3/28/22 – 4/15/22   Ulloa St. south side between 15th to 16th avenues

                                 Staging area approximately 10 ft. wide and approximately 50 ft. long

3/28/22 - 4/15/22    37th Ave. east side between Taraval St. to Santiago streets

                                 Staging area is 10 ft. wide and approximately 250 ft long

Train Service

4/11/2022              S Shuttle from West Portal to 21st Ave. has been providing temporary service to support the L bus line.

                              Discontinued

What to Expect:

New sewer and water lines

  • During excavation and installation, some driveways may be temporarily inaccessible
  • Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work
  • Heavy vibrations from the shoring and sheet piling work is expected for open trench work

Vehicle traffic

  • Temporary lane closures east of intersection where work will be performed

East and west side of 15th Ave. between Taraval and Ulloa streets

  • Posted no parking signs for the duration of work
  • Access may be delayed accessing residence, crews will allow safe access during construction
  • Sidewalk open for trenchwork

Temporary staging and construction areas

  • Posting of no parking signs along the staging areas
  • Posting of no parking signs in active construction areas

Time of Work:

Monday through Friday, from 8 a.m. to 5 p.m.

Saturday, April 9, 2022 from 8 a.m. – 7 p.m. Canceled

No work on  Saturday and Sunday

Traffic Impacts:

  • Some parking will be temporarily restricted in construction zones
  • Traffic lanes will be modified during active work
  • There will be dedicated flagger(s) to direct traffic and pedestrians
  • Temporarily close lane at intersections with detours

Impacts outside projects

Public Works  19h Ave.

PGE

3/25/22 – 4/15/22      29th Ave. and Taraval St.

                                 17th Ave. and Taraval St.

4/11/22 – 4/30/22      Taraval St. and 19th Ave.

                                  Taraval St. between 15th and 14th avenues

Anticipated – subject to change

Weekend Work

Saturday, April 9, 2022 from 8 a.m. – 7 p.m. Canceled