FINAL UPDATE: System reboot has been completed. IB train switchbacks have been cancelled & we are resuming regular #SubwaySvc operations. Bus shuttles will remain temporarily to provide supplemental svc. We will continue to monitor the system in case the issue reappears. (More: 22 in last 48 hours)

This page has older content

Please see Related Projects on this page for current project information. We are keeping this page as a record of SFMTA outreach.

Project Update and Forecast for the weeks February 22 through March 15, 2022

Service Affected
Accessibility
Bicycle
Motorcycle
Taxi
Driving
Transit
Walking
Website
Route(s) Affected

 

 

Details of work to be performed:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

                                   

Project Update and Forecast for the weeks February 22 through March 15, 2022

 

Taraval St.

North side of Taraval between 37th and 26th avenues

2/16/22 - 2/22/22    Potholing for sewer north side of Taraval St. and 32nd to 26th avenues heading east

2/23/22 - 3/11/22    Sawcut and construct north side of 32nd to 34th avenues and Sunset and Taraval streets

North side of Taraval between 26th and 18th avenues      

2/7/22 – 2/28/22     Potholing for sewer north side of Taraval St. and 26th Ave. heading east

2/18/22 – 3/1/22     Sawcut and construct north side of 26th to 25th avenues

15th Ave.

East side of 15th Ave. between Taraval and Ulloa streets

2/9/22 - 2/25/22      Sawcut and construct for waterline east side of 15th Ave. along sidewalk and driveway areas

2/25/22 - 2/28/22    Potholing for waterline west side of 15th Ave. along sidewalk and driveway areas

2/28/22 – 3/18/22   Sawcut and construct for waterline west side of 15th Ave. along sidewalk and driveway areas

Bus Stop Relocation (Temporary)

2/7/22 - 2/25/22       L Taraval line outbound northeast side of 26th Ave. and Taraval St. to northeast side of 27th Ave. and Taraval St. Weekday only Stop ID: 16622             

Temporary staging locations

2/7/22 - 5/25/22     37th Ave. east side between Rivera and Santiago streets

                                 Staging area is 10 feet wide and approximately 250 feet

2/7/22 – 2/25/22    26th Ave. northeast corner between Santiago and Taraval streets

                                 Staging area approximately 80 linear feet

2/9/22 – 2/25/22    15th Ave. east side between Ulloa and Vicente streets

                                 Staging area approximately 50 linear feet

2/14/22 - 3/4/22     25th Ave. east side between Santiago and Taraval streets

                                 Staging area approximately 80 linear feet 

2/11/22 - 5/25/22   36th Ave. between Santiago and Rivera streets

                                 Staging area is approximately 165 ft. long and 10 ft. wide

2/21/22 - 3/25/22   Quintera St. north side between 24th and 26th avenues

                                 Staging area to start 50’ east of 26th Ave. Length 350’ 

                                 Storing backfill materials and AC/concrete rubble materials

Pipeline Installation

2/9/22 - 2/25/22    15th Ave. East side between Taraval and Ulloa streets

                                 Installing new waterline

2/11/22 - 3/1/22     Taraval St. between 26th and 25th avenues intersection included

                                  Construction of sewer pipeline

2/22/22 – 3/9/22     Taraval St. north side between 25th and 24th avenues

                                  Installation of new sewer pipe north side

3/1/22 – 3/25/22     15th Ave. between west side Ulloa and Taraval streets

                                   Installation of waterline

2/23/22 – 3/15/22   Taraval St. between 34th and 33rd avenues north side

                                  Installation of new sewer pipe

What to Expect:

New sewer and water lines

  • During excavation and installation some driveways may be temporarily inaccessible
  • Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work
  • Heavy vibrations from the shoring and sheet piling work is expected for open trench work

East and west side of 15th Ave. between Taraval and Ulloa streets

  • Posted no parking signs for the duration of work
  • Access may be delayed accessing residence, crew will allow safe access during construction
  • Sidewalk open for trenchwork

Temporary staging areas

  • Posting of no parking signs along the staging areas

Time of Work:

Monday through Friday, from 8 a.m. to 5:00 p.m.

No work on Saturday and Sunday

Traffic Impacts:

Some parking will be temporarily restricted in construction zones

Traffic lanes will be modified during active work

There will be dedicated flagger(s) to direct traffic and pedestrians

Impacts outside projects