FINAL UPDATE: IB #FMarket cleared at Market and 7th. Regular service resuming. Expect residual delays. (More: 13 in last 48 hours)

Western Addition Traffic Signal Upgrades Phase 2

Project Introduction

The Western Addition Traffic Signal Upgrades Phase 2 project will upgrade traffic signals at 16 locations as recommended in the Western Addition Community Based Transportation Plan. Upgrades at 12 intersections include larger 12” signal heads and mast arms to enhance signal visibility, pedestrian signal improvements including pedestrian countdown signals and accessible (audible) pedestrian signals, updated streetlighting, and updated curb ramps. Project scope also includes pedestrian activated flashing beacons at 3 locations and 1 radar speed sign at one location. Fifteen of the 16 locations are on the High Injury Network.

This project is part of the Western Addition Community Safe Streets (WACSS) project. In addition to the signal scope from the Western Addition Traffic Signal Upgrades Phase 2 project, WACSS will deliver speed reduction strategies such as 20 MPH speed limits on eligible corridors, radar speed signs, quick-build projects, and a community education outreach campaign.

The Western Addition Traffic Signal Upgrades Phase 2 project was made possible in part by Proposition L Sales Tax dollars provided by the San Francisco County Transportation Authority and a federal Safe Streets and Roads for All (SS4A) grant.

Project Locations

  • Broderick Street and Turk Street, traffic signal upgrades
  • Divisadero Street and Turk Street, traffic signal upgrades
  • Divisadero Street and O'Farrell Street, traffic signal upgrades
  • Divisadero Street and McAllister Street, traffic signal upgrades
  • Scott Street and Turk Street, traffic signal upgrades
  • Pierce Street and Turk Street, traffic signal upgrades
  • Steiner Street and Turk Street, traffic signal upgrades
  • Fillmore Street and Turk Street, traffic signal upgrades
  • Fillmore Street and Hayes Street, traffic signal upgrades
  • Fillmore Street and McAllister Street, traffic signal upgrades
  • Eddy Street and Fillmore Street, traffic signal upgrades
  • Hayes Street and Webster Street, traffic signal upgrades
  • Buchanan Street and McAllister Street, radar speed sign
  • McAllister Street midblock crosswalk between Gough and Laguna streets, pedestrian activated flashing beacons
  • Turk Street midblock crosswalk between Gough and Laguna streets, pedestrian activated flashing beacons
  • Ellis Street and Fillmore Street, pedestrian activated flashing beacons
Project Timeline 
Design
Fall 2021 - Spring 2025
Pending
Solicit Bids from Contractors
Spring 2025 - Winter 2026
Pending
Construction
Winter 2026 - Winter 2027
Pending
Project Status
Detailed Design
Legislated
Improvements
SFMTA Drive and Parking icon
walking
SFMTA Accessibility icon
Neighborhoods
San Francisco County Transportation Authority logo
San Francisco Public Works logo
Vision Zero SF logo
Contact Information