Cable Car Maintenance Work: February 18 to October 21, 2025

Share this:
Service Affected
Accessibility
Transit
Neighborhoods Affected

Event Summary

As part of ongoing maintenance of the cable cars and their infrastructure, from Tuesday, February 18, and running until Tuesday, October 21, 2025, cable car maintenance will refurbish and reinstall all 21 sheaves (grooved wheels) that guide the underground cables and allow the cable cars to travel along their routes.

For complete project details, please visit the Cable Car Sheaves Upgrade Project webpage.

Muni Service Changes

The cable car lines will be broken up into the following four segments:

  • California segment
  • Hyde segment
  • Mason segment
  • Powell segment

When a segment is being worked on bus shuttles will provide service along that segment. At least one cable car line will remain open to the public during normal operating hours while sections are being upgraded.

Please refer to the table below for information on which segments will be work on which dates.

Notes:

  • All work is subject to weather and other conditions.
  • Be sure to receive real-time Muni service alerts via email or text by signing up through our Email and Text Subscriptions page.
Day Date Work Location Segments to Be Motorized
Tuesday 9/16/25 Clay and Hyde Hyde
Tuesday 9/23/25 Beach and Hyde Hyde
Wednesday 9/24/25 Beach and Hyde Hyde
Tuesday 9/30/25 Pacific and Hyde California and Hyde
Wednesday 10/1/25 Pacific and Hyde California and Hyde
Tuesday 10/21/25 Powell and Washington Powell, Mason and Hyde

Service Map

Map showing affect Cable Car routes and segments.

 