Interactive bus reroutes maps are available with temporary bus stop relocations during construction: https://www.sfmta.com/travel-updates/temporary-stop-relocations
Upcoming Saturday work
November 4
Taraval - 25th to 27th avenues: track work, excavate, track removal
Ulloa - Funston to 15th: sewer main
November 11
Taraval Street - 15th Avenue intersection: track area, thermite track welding
Ulloa - 14th avenue between Taraval and Ulloa: sewer line work
- Anticipating intersection closed at Ulloa
- Local access only between Taraval and Ulloa
Funston to 15th avenues: north side, sewer line work
- Expecting one way traffic in both directions
November 18
Taraval Street - 15th to 16th avenues: track area, install prefabricated rebar mats
The holiday construction moratorium will be observed from Thanksgiving until January 1, 2024. No construction activity will be performed in the commercial area along Taraval between Sunset and 16th Avenues between 7 am and 10 pm.
Business community resources
OEWD Announcements: Grants awarded up to $2,500 to bring Shared Spaces into compliance.
Shared Spaces Equity Grant for Design Compliance:
Apply for a Shared Spaces equity grant for design compliance | San Francisco (sf.gov)
No work is planned on Monday, September 4 as crews observe the Labor Day holiday
Pulling rails to Taraval between 22nd and 25th avenues on Thursday, August 31 more info about track Replacement on the L Taraval line.
Pulling rails to Taraval between 16th and 19th avenues on Monday, August 14 get more info about track Replacement on the L Taraval line.