Active Communities Plan - January Update #1
Update on the Active Communities Plan As we start the new year, we wanted to provide a status update on the timing of the Active Communities Plan. The team is taking a short break until mid-January to...
Update on the Active Communities Plan As we start the new year, we wanted to provide a status update on the timing of the Active Communities Plan. The team is taking a short break until mid-January to...
No construction scheduled Saturday, February 17 and 18th No Construction Presidents Day, February 19, 2024 February 14, 2024 - Rain day, minimal construction activity L Taraval Improvement Project...
L Taraval Improvement Project Segment B Update – February 26 – March 9, 2024 Work to install new rails, boarding islands, boarding ramps and curb ramps continues throughout the corridor. The last...
L Taraval Improvement Project Segment B Update – March 11 - 23, 2024 Work to install new rails, boarding islands, boarding ramps and curb ramps continues throughout the corridor. The last remaining...
L Taraval Improvement Project Segment B Update – March 25 - April 6, 2024 Work to install new rails, boarding islands, boarding ramps and curb ramps continues throughout the corridor. The last...
L Taraval Improvement Project Segment B Update – April 8 - 20, 2024 Infrastructure replacement work on sewer and water lines has been completed. The last remaining area of track installation work...
Segment B Update – April 22 - May 4, 2024 Infrastructure replacement work on sewer and water lines and rail installation has been substantially completed. Construction continues on boarding islands...
The L Taraval Improvement Project will begin curb-to-curb repaving of the entire Taraval corridor, starting May 6 for approximately three weeks. The construction area will be divided into three...
The K Ingleside Rapid Project will be considered for approval by the SFMTA Board of Directors at their Tuesday, March 5 meeting. The proposed project includes tools to improve transit travel times and...
3rd Street Quick-Build Board Hearing Dear Community Members,Thank you for your continued interest and participation in the 3rd Street Quick-Build project. The project’s outreach & design phase is...
At the February 6 SFMTA Board meeting, the Board of Directors unanimously approved the M Ocean View Transit and Safety Project. Through improvements like transit bulbs, boarding islands, new...
3rd Street Quick-Build Board Hearing Dear Community Members,Thank you for your continued interest and participation in the 3rd Street Quick-Build project. The project’s outreach & design phase is...
On Tuesday, Feb. 20, we presented our three-month evaluation of the Valencia bike lane pilot to the SFMTA Board of Directors. You can watch a video of the presentation and the questions and comments...
Quick-Build Implementation: San Jose Avenue, J Church Safety and Accessibility Project Phase 2 Quick-Build Implementation, Intermittent Weekends April through August 2024 Dependent on Crew...
The SFMTA's Slow Streets Program is excited to share the latest updates and progress across the network, reflecting our commitment to enhancing safety and livability on San Francisco's neighborhood...
3rd Street Quick-Build Approved by SFMTA Board of Directors Dear Community Members,Thank you for your continued interest and participation in the 3rd Street Quick-Build project. The project was...
Event Summary Tulip Day is an annual event where Union Square Plaza is blanketed with 80,000 tulips in partnership with the Dutch Consulate, City of San Francisco, and the Alliance. Visitors are...
After a brief break San Francisco’s Biking and Rolling Plan: Active Communities is back in motion. We are renewing our focus on the plan’s policies. Strong and robust policies are what will form the...
The project team is working closely with the Ocean View community to determine where improvements need to be made. We will use this feedback to help shape our proposals. During the first round of...
Feedback received during the first round of outreach helped our project team develop initial proposals that we shared with the community in the fall of 2022. We have shared the proposals and received...
Hello, Neighbors! Welcome to the third edition of the Potrero Yard Modernization Project newsletter. Check out our updates since November to replace Muni's obsolete, century-old bus yard with a modern...
Thanks to the almost 1,600 respondents who gave us feedback on design details for the new trees and decorative sidewalks that will be a part of the Geary Boulevard Improvement Project. We have...
At the March 5, 2024 SFMTA Board of Directors meeting, the Board voted to approve the K Ingleside Rapid Project. Upgraded transit islands, a transit lane, pedestrian bulbs, new loading zones for...
This past summer, the Franklin Street Quick-Build team shared evaluation results from the implementation of intersection improvements on Franklin Street between Broadway and Lombard. The initial...
Implementation Update: Monday March 25, 2024 The 3 rd Street Quick-Build Project is substantially completed and the two-way bike lane is open and ready to ride as of Monday, March 25, 2024. Over the...