Upcoming Construction Contracts

Note: Please note that the projected bid dates are tentative advertisement dates and are subject to change. For the latest bid advertisement announcements, please log on to City & County of San Francisco's website: Bids and Contract Database, and click the Search by Category arrow to view the "Construction" Category.

 

Project ID: FC054

Title: Presidio Lifts

Forecasted Advertise Date: Spring 2019

Estimated Contract Cost: $3.800 M

Description: Procure and install new Vehicle Lifts to enable SFMTA staff to perform vehicle maintenance. This project will help to maintain the transit fleet in a State of Good Repair by facilitating routine vehicle maintenance and mid-life fleet overhauls. The scope of work for this project also includes ADA accessibility upgrades, such as striping, signage and upgrading curb ramps surrounding the facility.

 

Project ID: TF084

Title: Replacement of Manual Switch System Phase I

Forecasted Advertise Date: Spring 2019

Estimated Contract Cost: $2.500 M

Description: The objective for the Replacement of Manual Switch System Phase I is to replace five existing manual switches with new remotely operable switch units. The new units will be connected to Power Control Center via fiber optic network. New conduits and feeder cables will be installed from the switch locations to the last manhole.

 

Project ID: TO057

Title: 16th Street Improvement Project (formerly Muni Forward 22 Fillmore Transit Priority Phase II)

Forecasted Advertise Date: Summer 2019

Estimated Contract Cost: $25 – 30 M

Description: Design and construct transit priority and pedestrian safety improvements for the 22 Fillmore route along 16th Street, including transit-only lanes, transit bulbs and islands, new traffic signals, several pedestrian safety upgrades, and utility work. The project will transform and shape the 16th Street corridor by improving transit reliability, travel time, safety, and accessibility for all users while meeting the needs of current and future residents, workers, and visitors to this growing regional destination.

 

Project ID: TO068

Title: L Taraval Rail and Overhead Rehab Control Phase I and Phase II

Forecasted Advertise Date: Phase II Summer 2019

Estimated Contract Cost: Phase II $70 M

Description: Replace approximately 23,000 track feet of existing tie and ballast paved track along the L Taraval between Forest Side Avenue near West Portal to La Playa. Replace worn OCS special work, trolley wire and trolley poles west of 15th Ave./Taraval St. This project also includes MUNI Forward implementation of the L-Taraval Rapid Project which will implement engineering changes to improve safety and reliability, and reduce travel time between Ulloa/15th and Taraval/46th. Components include, providing traffic signals with transit priority, transit bulbs, pedestrian bulbs, adding or modifying boarding islands, adding or modifying accessible platforms, painting transit only lanes, and other related elements such as reconstructing curb ramps and relocating catch basins. In coordination with the project SFPUC will replace existing sewer with a twin sewer system; SFWD will install two parallel water mains, one on each side of the MUNI Tracks along the L-Taraval Line between Ulloa /14th Avenue and Taraval/36th Avenue. Public Works will be restoring the pavement at locations not covered by the track, sewer, and water replacement scope of work.

Phase I locations include SF Zoo to Sunset Blvd.

Phase II locations include Sunset Blvd. to West Portal.

 

Project ID: FC067

Title: MME HVAC and Boiler Improvement

Forecasted Advertise Date: Summer 2019

Estimated Contract Cost: $2.500 M

Description: Design and construct transit priority and pedestrian safety improvements for the 22 Fillmore route along 16th Street, including transit-only lanes, transit bulbs and islands, new traffic signals, several pedestrian safety upgrades, and utility work. The project will transform and shape the 16th Street corridor by improving transit reliability, travel time, safety, and accessibility for all users while meeting the needs of current and future residents, workers, and visitors to this growing regional destination.

 

Project ID: SC051

Title: Physical Security Enhancements for SFMTA Facilities and Yards

Forecasted Advertise Date: Summer 2019

Estimated Contract Cost: $1.000 M

Description: Implement near-term recommendations from the SFMTA's Physical Threat and Vulnerability Assessment. This project will enhance physical security at SFMTA’s rail, trolley car, motor coach and maintenance support facilities.

 

Project ID: TF059

Title: Islais Creek Bridge Overhead Reconstruction Forecasted Advertise Date: Fall 2019

Estimated Contract Cost: $10.000 M

Description: Modify the existing Overhead Catenary System and supporting structural frames along Islais Creek Bridge (located along 3rd Street between Marin Street and Cargo Street) to increase reliability and reduce maintenance. The work will be managed by SFPW and consist of replacing work trolley wires and related supports, modifying and reconstructing Overhead Catenary System special work, and modifying and reconstructing structural support frames following completion of the replacement bridge

 

Note: Please note that the projected bid dates are tentative advertisement dates and are subject to change. For the latest bid advertisement announcements, please log on to City & County of San Francisco's website: Bids and Contract Database, and click the Search by Category arrow to view the "Construction" Category.