California Street Safety Project

Project Timeline 
Summer to Fall 2019
Preliminary Engineering
Pending
Summer to Fall 2019
Outreach
Pending
Fall 2019
Legislation
Pending
End of 2019
Quick-Build Construction
Pending
Spring 2020
Road Diet Implementation
Pending
Project Status
Preliminary Engineering
Current

The California Street Safety Project will improve safety for those traveling on the corridor by reconfiguring the roadway from four lanes to three, upgrading crosswalks, daylighting and other safety improvements. California Street is part of the city’s Vision Zero High-Injury Network that consists of the 13 percent of all San Francisco streets that account for 75 percent of severe and fatal collision.

Background

On California Street from Arguello Boulevard to Park Presidio Boulevard, a roadway reconfiguration from four lanes to three will be implemented to improve safety for all road users. On this stretch of the corridor, there have been 57 injury collisions in the past five years, including 4 pedestrian-involved collisions. This segment of California Street also has a high rate of Muni-involved collisions, with 35 transit collisions in five years. At 8 to 9 feet wide, the travel lanes are not wide enough in this area for Muni vehicles, which are 10.5 feet wide. As a result, Muni vehicles must straddle multiple lanes, leading to sideswipe collisions. In addition, having multiple lanes in each direction can encourage higher traffic speeds and can make crossing the street more challenging for pedestrians. It is currently anticipated that these improvements will be constructed in spring 2020.

^Example of existing conditions and roadway reconfiguration on 25th Avenue. 

In tandem with this effort, on California Street from Arguello Boulevard to 18th Avenue, improvements will be installed, which will include daylighting, high-visibility crosswalks and pavement marking to improve safety for people of all ages on a street with historically high rates of injury-related collisions. This project is part of the Vision Zero Quick-Build Program. As part of our commitment to the program, these improvements will be installed by the end of 2019.

Proposed improvements include:

  • Daylighting - adding red painted curbs at intersection approaches to improve visibility for all road users
  • Reconfiguring the roadway from four lanes to three to include one lane in each direction, with a flexible center turn lane
  • Continental Crosswalks
  • Advanced Limit Lines
  • Signs
  • Signal timing adjustments to increase walking time for pedestrians

Evaluation and Timeline

Following the construction of the full project in spring 2020, the project team will gather post-data on collisions, travel time for Muni and private cars, vehicle speeds, yielding behavior of drivers to pedestrians, and traffic volumes .After evaluating the impacts of the project, SFMTA will review whether any adjustments are needed to ensure the project meets its safety goals.

 