Vision Zero Quick-Build Projects

The Vision Zero quick-build initiative is an SFMTA effort to quickly implement pedestrian and bicycle safety improvements on the Vision Zero High Injury Network. The Agency committed to delivering 15 quick-build projects through 2020, while also working on comprehensive longer-term street changes for major capital projects. The SFMTA believes that quick-build safety projects will decrease the number of people fatally and severely injured on San Francisco streets, resulting in progress towards the SFMTA’s Vision Zero goal.


Background

 

Every year in San Francisco, approximately 30 people lose their lives and over 500 more are severely injured while traveling on city streets. Quick-build projects are one tool that the SFMTA is using to help implement safety projects faster, on San Francisco’s High Injury Network, or the streets that engineering improvements can have the biggest impact in reducing traffic related fatalities and severe injuries.

On June 4th, 2019, the SFMTA Board of Directors passed a resolution that enables the Agency to deliver quick-build projects in a more efficient and expedited manner by streamlining project delivery. The policy change was in response to Mayor Breed’s and the SFMTA Board of Directors’ requests for sooner safety improvements on San Francisco streets. The SFMTA Board resolution modified the Transportation Code and thus far, has identified 15 street projects for delivering quick-build projects over the next 24-month period.

 


What are quick-build projects?

 

Quick-build projects are reversible, adjustable traffic safety improvements that can be installed relatively quickly. Unlike major capital projects that may take years to plan, design, bid and construct, quick-build projects are buildable within weeks and months and are intended to be evaluated and reviewed within the initial 24 months of construction. Typical quick-build type improvements include:

  • Paint, traffic delineators, and street signs
  • Parking and loading adjustments
  • Traffic signal timing
  • Transit boarding islands

The public and neighboring properties will be informed of these projects prior to construction and will have the opportunity to provide input at a public hearing. Additionally, the SFMTA, through its Vision Zero Safe Streets Evaluation Program, will analyze projects pre- and post-implementation to review outcomes and determine design effectiveness. These findings will be reported to the public on the SFMTA website as well as reported back to the SFMTA Board of Directors within 24 months. Evaluations will inform near-term modifications and long-term designs for streets.  

Since quick-build projects are focused on the High Injury Network, often where a longer-term project is planned, not all projects are suitable for quick-build implementation. The SFMTA will continue to work with its City and stakeholder partners on implementation of longer-term projects that include hardscape safety improvements and streetscape elements.

Learn more about our Safe Streets Evaluation Program by clicking on the button below.

Safe Streets Evaluation Program

 


Vision Zero

 

Vision Zero is a citywide policy passed in 2014 and it is a commitment to build better and safer streets, educate the public on traffic safety, enforce traffic laws, and adopt policy changes that save lives. The goal is to create a culture that prioritizes traffic safety and ensure that mistakes on our roadways do not result in serious injuries or death.

The 15 selected streets for quick build projects are located on the Vision Zero High Injury Network, the 13% of streets accounting for 75% of the City’s severe and fatal traffic injuries. In some cases, the quick build projects also stem from larger capital project efforts, aiming to redesign streetscapes and transportation infrastructure for safety and livability improvements.

The quick build projects initiative is one of many efforts to help achieve the City’s Vision Zero goals. Read more about other City efforts in the San Francisco Vision Zero Action Strategy.

Read the Vizion Zero Action Strategy

 


Quick Build Project Summary Table

 

Corridor Scope Next Milestone Expected Completion
6th Street
(Market to Folsom)
Lane reduction, painted safety zones, left turn restrictions in advance of larger construction project to install sidewalk widening and signals   Completed 9/2019
7th Street
(Townsend to 16th)
Protected bikeway   Completed 7/2019
Brannan Street
(Embarcadero to Division)
Bike lanes in advance of larger construction project to install sidewalk widening, raised bikeways, protected intersection   Completed 11/2019
Howard Street (3rd to 6th) Protected bikeways, curb management   Completed 4/2019
Taylor Street (Market to Sutter) Lane reduction, painted safety zones, protected left turn, left turn restriction in advance of larger construction project to install sidewalk widening   Completed 6/2019
Terry Francois Boulevard (Mariposa to Mission Bay) Protected bikeways, curb management   Completed 8/2019
3rd Street (Mission to Townsend) Transit-only lane, painted safety zones, ped head start, transit stop changes in advance of larger construction project to install bulbouts Complete substantial construction 2/2020 2/2020
5th Street (Market to Townsend) Protected bikeways, bike signals, transit boarding islands in advance of larger construction project to install raised bikeways  Complete substantial construction 12/2019 Striping, signs: 12/2019
Boarding islands: Spring 2020
7th Street Protected bikeway, transit and school boarding islands, lane reduction, bike signals, curb management, transit stop changes Public hearing 12/11/2019 in coordination with D6 Office open house event Summer 2020
Alemany Boulevard (Stoneybrook to Putnam) Protected bikeways Environmental review Winter 2019-2020
Beale Street (Market to Folsom) Protected bikeways, transit-only lane, curb management in advance of larger construction project to install sidewalk widening Environmental review Winter 2019-2020
California Street (Arguello to 18th) Daylighting, advanced limit lines, crosswalk upgrades Begin construction 12/2019 Winter 2019-2020
The Embarcadero (Mission to Folsom) Protected bikeways Ongoing outreach and design, environmental review Summer 2020
Evans Avenue/Hunters Point Blvd/Innes Avenue (Jennings to Arelious Walker) Design scope in development Ongoing outreach and scope development 2020
Folsom Street (2nd to 5th) Protected bikeway Ongoing outreach and scope development 2020
Geneva Avenue (Mission to Prague) Daylighting, painted safety zones, curb management, transit stop changes Begin construction 4/2020 Summer 2020
Golden Gate Avenue (Market to Polk) Design scope in development Ongoing outreach and scope development 2020
Howard Street (Embarcadero to 3rd) Protected bikeway, transit boarding islands, lane reduction, curb management Public hearing 12/11/2019 in coordination with D6 Office open house event Summer 2020
Indiana Street (24th to Cesar Chavez) Protected bikeways, traffic calming, painted safety zones Complete substantial construction 11/2019 11/2019
Leavenworth Street (McAllister to O'Farrell) Design scope in development Ongoing outreach and scope development 2020
Market Street (Octavia to Steuart) Car-free street, transit-only lane, bike improvements, curb management in advance of larger construction project to install raised bikeways, sidewalk widening Begin construction 12/2019 Winter 2019-2020
Mission Street (Trumbull to Geneva) Daylighting, painted safety zones, curb management, transit stop changes Begin construction 4/2020 Summer 2020
Townsend Street (3rd to 8th) Protected bikeways, pedestrian walkways, transit boarding islands, transit stop changes Finish construction of block-long island between 4th and 5th streets 5th to 7th blocks: 12/2018
3rd to 5th blocks: 2/2020
7th to 8th block: Spring 2020
Williams Avenue (3rd to Vesta/Phelps) Design scope in development Ongoing outreach and scope development 2020
Valencia Street (19th to Cesar Chavez) Protected bikeways, curb management, school boarding island Ongoing outreach and design Spring 2020
Last updated: 11/27/19

 

Quick Build Projects

 

Below are the initial set of 15 projects that the SFMTA committed to delivering as quick-build projects within 24 months. The SFMTA Board of Directors could add additional projects to the quick-build list with future resolutions.

 

2019 Projects

2020 Projects