Project Update
Thursday, February 7, 2013
Dear Neighbor, Last week, I reported on the progress we've made since last year on relocating the extraction site of the Central Subway's tunnel boring machines from Columbus Avenue to a less...
Project Update
Friday, October 4, 2013
Construction Update October 5-14, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station construction...
Project Update
Friday, April 28, 2017
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, September 25, 2015
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, February 8, 2013
Construction Update Feb. 9-18, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned to occur in...
Project Update
Friday, June 28, 2013
Construction Update June 29-July 15, 2013 During the next 17 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH...
Project Update
Friday, March 28, 2014
Construction Update March 29 - April 7, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Project Update
Friday, November 15, 2013
Construction Update November 16-25, 2013 During the next 10 days, tunneling and tunneling preparatory work will continue in SoMa, Union Square and North Beach. Work to prepare for station...
Project Update
Friday, September 16, 2016
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, October 16, 2015
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, November 2, 2012
Construction Update North Beach Utility Relocation This week Central Subway crews continued sewer line construction in North Beach. Sewer work is planned to continue next week, and this week's...
Project Update
Friday, August 23, 2013
Construction Update August 24-September 2, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, demolition of the Pagoda Palace...
Project Update
Friday, May 16, 2014
Note: Updated information as of 6:02 pm, 5/16/14. At 4th and Bryant I-80 off-ramp, three lanes may be closed on weeknights from 12 a.m. to 5 a.m. and one lane may be closed during the daytime from 10...
Project Update
Friday, May 31, 2013
Construction Update June 1-10, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned in Chinatown or...
Project Update
Friday, June 21, 2013
Construction Update June 22-July 1, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. In North Beach, Pagoda Palace demolition contractor MH...
Project Update
Friday, June 20, 2014
Construction Update June 21 - June 30, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Project Update
Friday, December 6, 2013
Construction Update December 7-16, 2013 We completed an important construction milestone last week as our tunneling contractor and TBM Mom Chung successfully and safely tunneled under Market Street...
Project Update
Thursday, July 2, 2015
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, May 23, 2014
Construction Update May 24 - June 2, 2014 During the next 10 days, Central Subway work will continue at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Project Update
Friday, April 22, 2016
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...
Project Update
Friday, July 18, 2014
Project Advancements July 19 - July 28, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief updates...
Project Update
Friday, June 7, 2013
Construction Update June 8-17, 2013 During the next 10 days, construction to prepare for tunneling will continue in SoMa and Union Square. No Central Subway construction is planned in Chinatown or...
Project Update
Friday, September 7, 2012
Construction Update North Beach Utility Relocation Next Thursday, September 13, the contractor plans to begin installing a sewer manhole within the Central Subway construction zone in North Beach. To...
Project Update
Friday, November 14, 2014
Project Advancements November 15 - November 24, 2014 During the next 10 days, Central Subway work continues at sites in SoMa, Union Square, Chinatown and North Beach. This section contains brief...
Project Update
Friday, September 22, 2017
Thank you for your interest in the Central Subway Project, which is a significant project in the history of San Francisco's public transportation network. This project is the first underground line...