October 2025 Update
The project team is hard at work on the Howard Streetscape project design and construction for the Folsom Streetscape project. Come visit us this Sunday, October 5th, 2025, at SOMA Sunday Streets on Russ between Folsom and Howard Streets from 12 to 4 PM to learn more about these projects!
Folsom Streetscape
Construction on the Folsom Streetscape project is over halfway done and on track to reach substantial completion by October 2026. The crews have completed big upgrades to the 100-year-old sewer system and electrical work for signals and new lights. They are now installing water mains and getting ready to work on sidewalks and corners.
- View the updated Folsom Streetscape Project illustrative map!
- Public Works will lead the construction phase - subscribe to receive construction updates at https://www.sfpublicworks.org/FolsomSOMA.
- Review the Construction FAQs.
- Review the Office of Economic and Workforce Development Folsom Street Small Business Resource Guides .
Howard Streetscape
The Howard Streetscape project is reaching a new milestone: design completion. This means that all the construction plans are almost complete, and we’ll soon start looking for contractors to bid on the project. This year, we worked closely with local residents, businesses, and property owners to make improvements based on feedback from last year’s Open House. We expect construction to start in late 2026.
- View the final design here!
- Current
Community Engagement

- 1,300 questionnaire Reponses
- Meetings with 20 community groups
- 550 people attended open houses
- Knocked on 165 businesses’ doors
- 110 meetings with local businesses
- 150 business loading surveys completed
- 27,000 open house notification postcards delivered
- Distributed 600 open house notification posters
- 100s of hours of staff outreach
The SFMTA has worked in close collaboration with neighbors, local businesses, community groups and users of the Folsom and Howard Street corridors since initiation of the project.
In Winter 2016, the SFMTA held two open houses and conducted an online survey to take feedback on their values and priorities. In April 2017, two open houses were held to show possible alternatives to the public and request feedback. In January 2019, the SFMTA presented the final proposed long-term designs of the corridor at two open houses.
By working closely with the community to align project goals, the SFMTA was able to secure legislative approval of the project in Spring 2019. We will continue to engage the community in coordination with our partners at Public Works to finalize the public realm elements of the project and to inform users and residents of construction updates.
Project Timeline
Folsom-Howard Planning Phase/Quick-Build Projects/Legislation
- Predevelopment: Fall 2015 to Fall 2016
- Community Values Open Houses: December 2016
- Community Outreach and Planning: Winter 2016 to Summer 2019
- Folsom Near-Term Open Houses: July 2017
- Folsom Near-Term Public Hearing: Fall 2017
- Folsom Near-Term Legislation: Fall 2017
- Folsom Near-Term Changes Installed: Winter 2018
- Howard Near-Term Open Houses: July 2018
- Howard Near-Term Legislation: October 2018
- Howard Near-Term Changes Installed: Winter 2019
- Proposed Alternative for Long-Term Changes Open Houses January 2018
- Long-Term Legislation: Spring/Summer 2019
Folsom Streetscape Project - Detailed Design/Construction
- Detailed Design: 2019 to 2022
- Issue Contract and Notice to Proceed: 2023
- Construction: 2024 to 2026
Howard Streetscape Project - Detailed Design/Construction
- Detailed Design: 2024
- Issue Contract and Notice to Proceed: 2026
- Construction: 2026 to 2029